WMS were delighted to win via competitive tender the above
works and to work closely with Surveyors RTP who have offices in Falmouth and Bodmin. http://www.rtpsurveyors.co.uk/
This complex external painting contract included extensive
roof, chimney & window repairs prior to commencement. Specialist window repair products were utilised to carry therepair along with a specification drawn up by our contract partner Akzo- Nobel
with Specification manager being Stephen Oakley .
The three Truro city centre builds one of which was grade 2
listed were scaffolded and netted to ensure public and staff safety and all
buildings were pressure washed before starting.
Two of our apprentices
experienced work under supervision from site supervisor and redecoration
manager on this programme and this will
All three buildings were completed with 4 weeks which was
ahead of schedule and under budget .
Back to Case Studies